Domain Specific Languages MQP Schedule

Week 1 (Oct. 25 - Oct. 31)

Tasks

  • Background Research of DSL's
  • Propose Topic

Comments

  • Topic chosen is creating a uniform approach to designing and developing domain specific languages
  • Discussed topic with advisor and planned further research
  • Decided upon creating an example DSL using the process we will be creating

Week 2 (Nov. 1 - Nov. 7)

Tasks

  • Continue background research of DSL's
  • Background research on software reuse
  • Background research on Rational Unified Process
  • Set up Wiki for project

Comments

  • Discussed what components we may wish to encorporate into our process with advisor

Week 3 (Nov. 8 - Nov. 14)

Tasks

  • Create Vision document
  • Create work schedule for project
  • Start identifying artifacts for Domain Specific Language process
  • Start Glossary of Terms for project

Comments

Week 4 (Nov. 15 - Nov. 21)

Tasks

  • Continue identifying artifacts for process
  • Start identifying and organizing different phases that should be present in the process
  • Identify the views that can be used in the domain mapping process
  • Start writing the final report

Comments

Week 5 (Nov. 22 - Nov. 28)

Tasks

  • Finish identifying artifacts for process
  • Continue identifying and organizing different phases that should be present in the process

Comments

Week 6 (Nov. 29 - Dec. 5)

Tasks

  • Finalize all aspects of the process for developing Domain Specific Languages

Comments

Week 7 (Dec. 6 - Dec. 12)

Tasks

  • Review all steps in in the process and plan for development of exemplar DSL
  • Design example application to be done in DSL and general purpose language

Comments